Mold installation and removal steps
One: mold installation
1. Make sure the injection molding machine is powered on.
2 Click the manual button of the injection molding machine to make the injection molding machine in the manual state.
3. Click the injection molding oil pump button to start the injection molding oil hydraulic system.
4. Deliver the mold in place and confirm that the mold matches the production parts.
5. Prepare the sling.
6. Use a sling to lift the mold slowly, slightly higher than the injection molding machine, and move the sling to make the mold above the installation position. Be careful not to let the mold hit the surveillance camera and manipulator.
7. Slide the protective sleeve of the guide post of the injection molding machine to a suitable position and slowly lower the mold. The operator should hold the top of the mold to prevent the mold from shaking violently. The operator must control the mold and prohibit the mold from hitting the guide post. (The impact of the guide post will cause uneven deformation and damage the sealing performance of the hydraulic system)
8. Lower the mold to an appropriate position, install the positioning flange and protective ring, and adjust the mold and sling so that the mold flange and protective ring fit into the injection hole of the injection molding machine.
9. Close the sliding doors on both sides of the injection molding machine, and click the mold adjustment button of the injection molding machine to enter the mold adjustment state.
We believe quality begins with mould design capability and consider it to be the key to successful mould making.
car coolant plastic water tank mouldinjection mouldautomotive part mould1+1 cavity718 mould steelcold runner
Tuofang company is specialized in designing and manufacturing Plastic Injection.
No. 71 Hequ Road, Chengjiang Street of Huangyan, Taizhou City, 318020, Zhejiang Province, China